Illustration. Suryakiran Installations, a small solar subcontractor in Ghaziabad, erected mounting structures, laid DC cabling and installed modules on a 2 MW rooftop project for Brightgrid EPC Private Limited. Its bills came to ā¹33,95,000 across four milestones. Brightgrid paid the advance, then stopped. First it blamed net-metering approval. Then it said the performance ratio test had failed. Finally it sent a debit note for ādamaged modulesā. Suryakiranās owner had commissioning photographs, a signed joint inspection report and nothing to show for them. That is the kind of file an MSEFC payment dispute lawyer is built for.
The names are invented, but the pattern is not. Payment disputes before the council are rarely about whether work was done. They are about what the buyer says it is entitled to hold back, and for how long. You can hire Advocate BK Singh for MSME, recovery, commercial or arbitration cases, and this page explains how he approaches a contested payment dispute before the Micro and Small Enterprises Facilitation Council.
Key facts at a glance
- Section 15 caps the payment period at 45 days from acceptance or deemed acceptance.
- Deemed acceptance applies if the buyer raises no written objection within 15 days.
- Section 17 makes the buyer liable for the amount due with Section 16 interest.
- Section 18 lets any party to the dispute refer it to the council.
- Only micro and small suppliers can use the delayed-payment chapter, not medium enterprises.
- Supplies made before Udyam registration are not covered (Silpi Industries, 2021).
What Does an MSEFC Payment Dispute Lawyer Do for a Supplier?
An MSEFC payment dispute lawyer works out exactly how much the buyer owes, separates genuine disputes from excuses, and presents the supplier's claim to the council in a form it can decide quickly. The lawyer then represents the supplier through conciliation and arbitration, and protects the result if the buyer goes to court.
The first job is diagnosis. A buyer who has not paid will usually have given some reason, even a thin one. The lawyer needs to know whether that reason is backed by any document. A debit note issued four months after commissioning, with no inspection report attached, is a very different thing from a defect notice sent within a week of delivery and signed by both sides.
The second job is translation. Suppliers know their trade. They do not always know which facts matter in law. For a solar subcontractor, the date the commissioning certificate was signed matters more than the date the last module was bolted down. The date a joint measurement was recorded matters more than the date the invoice was raised. A good lawyer turns the supplier's story into dates, documents and statutory consequences.
When you need an advocate rather than a consultant
If the buyer has already disputed the bill in writing, raised a counterclaim or engaged lawyers, the matter is heading towards arbitration and possibly court. At that point an enrolled advocate should be leading. A consultant can help assemble invoices, but only an advocate can appear in a Section 34 challenge or file an execution petition when the time comes.
What Counts as a Payment Dispute the Council Can Decide?
The council can decide a dispute about any amount due under Section 17 from a buyer to a micro or small supplier for goods supplied or services rendered. The supplier must have been registered before the supply, must be micro or small, and must not be a pure trader reselling goods bought from others.
The buyer, under Section 2(b), is anyone who buys goods or receives services from a supplier for consideration. That covers private companies, partnerships, government departments, public sector undertakings and other MSMEs. It does not matter that the buyer is far larger than the supplier, or that it is in another State.
Some disputes fall outside the council's reach. A medium enterprise cannot use the delayed-payment chapter even if it is registered on Udyam. A supplier that merely buys and resells panels without any manufacturing or service element is generally outside it too. And a claim for goods supplied before the Udyam certificate was issued cannot be pursued under the Act, though it may still be recovered through an ordinary suit.
Questions about the supplier's own status often decide the case before any merits are heard. Our page on MSME Act dispute resolution explains how classification works, and why the date on your certificate needs checking before anything is filed.
Where Do Solar EPC Subcontract Payments Usually Get Stuck?
Solar EPC subcontract payments get stuck at the milestones that depend on someone other than the subcontractor: DISCOM inspection, net-metering approval, the performance ratio test, and the developer's own payment to the EPC contractor. Each gives the buyer a convenient reason to hold money that the subcontractor has already earned.
A typical subcontract splits payment into stages. Perhaps 10% on mobilisation, 50% on material delivery, 25% on installation and 15% on commissioning. The subcontractor's scope ends at mechanical completion or commissioning. The EPC contractor's scope extends to grid synchronisation, performance testing and handover to the plant owner. Problems arise when the EPC contractor treats its own downstream milestones as conditions for paying the subcontractor.
The common excuses run as follows:
- Net-metering approval is pending with the DISCOM, so the project is not complete.
- The performance ratio test showed a shortfall, so a deduction will be made.
- Some modules were found cracked or damaged, and replacement cost will be recovered.
- The plant owner has not released our payment, so we cannot release yours.
- The retention bank guarantee has not been submitted.
Some of these are contractual points worth examining. Others confuse two contracts. If the subcontract makes commissioning the final milestone and commissioning was certified, a pending net-metering approval is the EPC contractor's problem. If modules were damaged after handover, during the EPC contractor's own testing, the cost is not the subcontractor's to bear.
Which Buyer Deductions Hold Up and Which Do Not?
Deductions hold up when the contract allows them, the buyer raised them in writing at the right time, and documents support the amount. They fail when they appear late, rest on another contract, or are simply asserted without proof. The table below shows how we usually assess common deductions in solar subcontracts.
| Deduction claimed by buyer | Typical reason given | What we look for | Our usual assessment |
|---|---|---|---|
| Performance ratio shortfall | Plant output below guaranteed level | Whether PR guarantee is in the subcontract at all, and who controlled testing | Weak if the guarantee sits only in the EPC contract with the plant owner |
| Damaged modules | Cracks found during inspection | Joint inspection at handover, photographs, who handled modules afterwards | Weak if raised long after a clean handover |
| Delay damages | Late completion | Extension requests, late site access, late material supply by buyer | Depends on the delay record; often overstated |
| Retention | Defect liability period running | Retention clause, period, release conditions | Valid until the period ends, then interest-bearing |
| Back-to-back withholding | Plant owner has not paid | Whether payment is legally linked, Section 24 override | Generally not a defence for a micro or small supplier |
| Material shortage | Less cable or structure received than billed | Delivery challans, GRNs, site receipts | Valid only to the extent of proven shortage |
The assessments above are general. Every contract reads differently, and a well-drafted subcontract can make a deduction valid that would otherwise fail. That is why the first meeting always starts with the contract, not the invoices.
Practical tip: answer every debit note in writing within a few days, even with a short holding reply. An unanswered debit note looks like acceptance by the time it reaches the council.
How Does the 45-Day Rule Apply to Milestone Billing?
For milestone billing, the 45-day clock under Section 15 starts from the day the buyer accepted the goods or services for that milestone, or is deemed to have accepted them. If the buyer did not object in writing within 15 days of delivery or performance, deemed acceptance applies, and payment falls due within 45 days of that date at the latest.
The practical question is what counts as acceptance for each milestone. For material delivery, a signed delivery challan or goods receipt note usually does it. For installation, a joint measurement record or the EPC contractor's site engineer signing off a completion sheet. For commissioning, the commissioning certificate itself.
Buyers sometimes argue that acceptance only happens when the whole plant is accepted by the plant owner, months later. That argument rarely survives a close reading of the subcontract and the supplier's records. If the EPC contractor received modules, logged them in its stores and then had them installed, it is hard to say it never accepted them. The law on delayed payment recovery under the MSMED Act turns on these acceptance dates.
Any contract term that allows more than 45 days is overridden by Section 15 to the extent of the excess. A clause granting the buyer 90 days after the plant owner's acceptance does not bind a micro or small supplier beyond the statutory limit.
What Should a Solar Subcontractor Keep on File From Day One?
A solar subcontractor should keep every document that fixes a date: the signed subcontract, delivery challans, GRNs, joint measurement records, completion sheets, the commissioning certificate, debit notes with replies, and any email in which the buyer admits the work is done. Disputes are decided on these papers, often a year or more later.
Most subcontractors keep invoices carefully and everything else loosely. The invoice proves only that you asked for money. It does not prove the buyer received the material, that the installation was checked, or that the commissioning was signed off. Those facts sit in site papers that tend to get lost when a project team moves on to the next job.
We suggest a simple habit. At the end of each milestone, scan the signed site document and email it to the buyer's project manager with a short covering line: āPlease find attached the signed installation completion sheet for Block C. Our milestone bill follows.ā That email does two things. It creates a dated record that the buyer received the document, and it starts the 15-day window within which any objection must be made in writing.
- Signed subcontract or purchase order, with any amendments and scope changes.
- Delivery challans and the buyer's goods receipt notes for modules, structures and cable.
- Joint measurement records and installation completion sheets for each block.
- Commissioning certificate and any punch list, with proof that punch points were closed.
- Every debit note received, with your written reply and the date sent.
- Ledger confirmations or emails in which the buyer accepts the balance.
If those records are already scattered across WhatsApp groups and site engineers' phones, gather them now, before the dispute hardens. Screenshots with dates visible are better than nothing, and the originals can often be recovered later.
How Is the Claim Amount Worked Out When Part Payments Were Made?
When part payments were made, each payment is first set against the oldest outstanding bill unless the buyer specified otherwise, and interest is then computed on the reduced balance from the date of payment. The council expects to see this done bill by bill, with dates, rather than as one rounded figure.
Take a simple case. A milestone bill of ā¹10 lakh fell due on 1 March. The buyer paid ā¹4 lakh on 15 June. Interest runs on ā¹10 lakh from 1 March to 15 June, and on ā¹6 lakh after that. If the buyer's payment advice said the ā¹4 lakh was for a later bill, the allocation changes, and so does the interest. Suppliers often lose a lakh or two of interest simply by allocating payments carelessly. A clean schedule also makes it harder for the buyer to argue that the supplier has inflated the claim.
How Much Interest Accrues on the Disputed Amount?
Interest accrues under Section 16 at three times the RBI Bank Rate, compounded with monthly rests, from the due date until payment. On ā¹33,95,000 at the 5.75% Bank Rate that applies from 7 October 2026, that is 17.25% a year or 1.4375% a month, and the figures grow quickly.
After six months the interest is ā¹3,03,546 and the total due is ā¹36,98,546. After a year, interest reaches ā¹6,34,232 and the total ā¹40,29,232. After two years the interest is ā¹13,86,946, bringing the total to ā¹47,81,946. Buyers who hold money for two years on weak excuses end up paying far more than they saved.
| Period after the due date | Growth factor | Interest (ā¹) | Total due (ā¹) |
|---|---|---|---|
| 6 months | 1.0894 | ā¹3,03,546 | ā¹36,98,546 |
| 12 months | 1.1868 | ā¹6,34,232 | ā¹40,29,232 |
| 18 months | 1.2929 | ā¹9,94,484 | ā¹43,89,484 |
| 24 months | 1.4085 | ā¹13,86,946 | ā¹47,81,946 |
Principal ā¹33,95,000. Interest compounded monthly at three times the RBI Bank Rate (5.75% from 7 October 2026), that is 17.25% a year or 1.4375% a month. Check the Bank Rate in force for your period.
For a milestone claim, the interest schedule must run separately for each milestone from its own due date. A disputed portion and an undisputed portion should also be shown separately, so that the council can award interest on the undisputed amount even if it wants more evidence on the rest. Section 23 adds that the buyer cannot deduct this interest as an expense for income tax.
How Does the Section 18 Reference Work in a Payment Dispute?
The Section 18 reference is the formal step that brings the payment dispute before the council. It is usually filed through MSME Samadhaan or directly with the council, depending on the State, with the invoices, acceptance proof, Udyam certificate and an interest working attached.
- Contract and status check. We confirm the supplier was micro or small and registered before the supplies, and that the activity is manufacturing or services rather than pure trading.
- Claim schedule. Each invoice or milestone bill is listed with its acceptance date, Section 15 due date, amount paid and amount outstanding.
- Deduction analysis. Every debit note and deduction is listed with the buyer's stated reason and the supplier's answer, so the council sees the dispute in one place.
- Demand notice. Where none has been sent, a legal notice citing Sections 15, 16 and 24 often prompts a reply that clarifies the buyer's real position.
- Filing the reference. The reference goes to the council with the documents and the interest working. Errors here cause delay, so we check every annexure.
- Council notice to buyer. The council issues notice and fixes a conciliation date. The buyer may file a written reply.
For a supplier filing for the first time, our MSME Samadhaan filing representation page sets out what the portal asks for in general terms. We do not rely on screen-by-screen guides, because portals change and councils follow their own practice.
What Happens at Conciliation in a Payment Dispute?
At conciliation, the council or an institution it appoints tries to help the parties reach a settlement under Sections 65 to 81 of the Arbitration and Conciliation Act, 1996. In payment disputes this usually means narrowing the deductions, agreeing a principal figure and negotiating how much interest the buyer will pay.
A payment dispute often settles here because the buyer sees the interest schedule for the first time. A buyer who was arguing over a ā¹4 lakh debit note may decide it is cheaper to concede the note than to face interest on the full ā¹33 lakh for another year.
Our approach at conciliation is to decide in advance what the supplier would accept, what it would never accept and what it needs in writing. A settlement that pays principal in six instalments with no default clause is weaker than one that pays less interest but revives the full claim on any missed instalment. A settlement agreement signed in conciliation has the status of an arbitral award under Section 74 of the 1996 Act, so it can be enforced if the buyer defaults.
When conciliation fails, the council records that and moves to arbitration. The MSEFC dispute settlement lawyer page discusses settlement tactics at more length.
How Is the Payment Dispute Decided in Arbitration?
In arbitration, the council decides the payment dispute on the pleadings, documents and any oral evidence, and issues a reasoned award. The supplier must prove the supplies, acceptance and the amount due. The buyer must prove each deduction and any counterclaim. Burden matters, and most solar disputes turn on it.
For Suryakiran in the illustration, the burden analysis would be straightforward. Suryakiran proves the four milestone bills, the commissioning certificate and the joint inspection report. Brightgrid must then prove that the performance ratio guarantee applied to the subcontractor, that the modules were damaged while in Suryakiran's control, and that the damage cost what it claims. If Brightgrid cannot produce a joint inspection showing damage at handover, its debit note has little foundation.
Counterclaims are allowed in council arbitration, as the Supreme Court confirmed in Silpi Industries (2021). In solar disputes, EPC contractors sometimes counterclaim for liquidated damages that the plant owner imposed on them. The question is whether the subcontract passes those damages down, and whether the delay was really caused by the subcontractor. Late drawings, late site readiness and late supply of modules by the EPC contractor itself are common answers.
Which Jurisdiction and Limitation Points Arise?
The main jurisdiction point is Section 18(4): the council where the supplier is located has jurisdiction, even if the buyer and the project are elsewhere. The main limitation point is that the Limitation Act applies to council arbitration, so claims older than three years from the due date are at risk.
A Ghaziabad subcontractor working on a project in Rajasthan for an EPC contractor based in Gujarat can still go to the council with jurisdiction over Ghaziabad in Uttar Pradesh. Buyers sometimes argue that a contract clause choosing another seat overrides this. Section 24 gives the delayed-payment provisions overriding effect, and the statutory right to approach the supplier's council usually prevails.
On limitation, look for anything the buyer signed acknowledging the debt: a ledger confirmation, an email agreeing to a payment plan, a letter promising release after net metering. A written acknowledgment signed before the period expires restarts limitation under Section 18 of the Limitation Act. Keep those documents safe.
When Should a Payment Dispute Go Somewhere Other Than the Council?
A payment dispute should go elsewhere when the supplier is not eligible under the Act, when the claim is mostly for supplies before registration, when the buyer has given a cheque that has bounced, or when the debt is undisputed and above ā¹1 crore against a company. The table compares the main options.
| Route | Fits when | What it gives | Watch out for |
|---|---|---|---|
| MSEFC reference | Registered micro or small supplier, supplies after registration | Statutory interest, home forum, 75% deposit on challenge | Status objections, counterclaims |
| Commercial suit | Claim of ā¹3 lakh or more outside the Act | Full civil remedies, interim orders | Mandatory pre-institution mediation under Section 12A |
| Summary suit | Written contract or acknowledged debt | Defendant needs leave to defend | Leave granted if a real dispute exists |
| Section 138 complaint | Buyer's cheque dishonoured | Criminal liability; interim compensation up to 20% | 30-day notice and filing deadlines |
| IBC Section 9 | Undisputed debt of ā¹1 crore or more from a company | Pressure on management | Any genuine pre-existing dispute ends it |
A payment dispute with real arguments on both sides is usually unsuitable for insolvency proceedings, because the existence of a dispute defeats a Section 9 application. Our commercial court case lawyer page covers the civil suit route for claims the council cannot hear.
What If the Buyer Is a Large Company or a Government Body?
A large private company faces disclosure and tax consequences for late payment to micro and small suppliers, which often encourages settlement. A government department faces fewer such pressures, so the council route and the award carry most of the weight. The supplier's strategy should reflect who the buyer is.
For companies, Section 22 requires disclosure of amounts owed to micro and small enterprises in their annual accounts. Companies that pay beyond 45 days must also file MSME Form I with the Ministry of Corporate Affairs every half year. Section 43B(h) of the Income-tax Act means a buyer cannot claim a tax deduction for payments to micro and small enterprises until they are actually made, if made beyond the permitted period. These provisions give a supplier useful talking points in conciliation.
A government department does not claim income tax deductions in the same way, so Section 43B(h) adds little pressure there. Public sector undertakings sit somewhere in between. Against a government buyer, the strength of the council award and the 75% deposit rule do most of the work.
Honest limit: if the buyer is in serious financial trouble or already facing insolvency proceedings, an award may be hard to recover in full. In that situation we discuss early settlement, security and the timing of claims against the insolvent buyer.
What Happens After the Award Is Made?
After the award, the buyer has three months, extendable by 30 days, to challenge it under Section 34. To have the challenge heard, the buyer must deposit 75% of the awarded amount under Section 19. If there is no challenge, or it fails, the supplier enforces the award under Section 36 like a court decree.
The deposit requirement is the supplier's best protection. It turns a buyer's delaying challenge into an expensive one. The court can also release part of the deposit to the supplier during the challenge, and we ask for that in suitable cases.
Once enforceable, the award can be executed against the buyer's bank accounts, receivables and property. For an EPC contractor, receivables due from plant owners are often the most practical target. You can hire Advocate BK Singh for MSME, recovery, commercial or arbitration cases at the enforcement stage as well, even if someone else handled the arbitration.
Why Hire Advocate BK Singh for MSEFC Payment Disputes?
Because payment disputes are won on detail, and his practice is built around the detail of MSME delayed-payment law.
- Regular MSEFC and MSME work. Advocate BK Singh handles delayed-payment references, conciliation and council arbitration as a core part of his practice. He knows how councils approach deductions and counterclaims.
- Deduction-by-deduction analysis. Each debit note is tested against the contract and the records. Councils respond better to a clear schedule than to a general complaint.
- Recovery and commercial litigation experience. When a dispute cannot go to the council, he can take it to a commercial court or a summary suit. The client does not have to start again with someone new.
- Arbitration practice beyond the council. Section 34 challenges and Section 36 execution are handled in-house. The same team carries the file from start to finish.
- Appearances across major forums. He appears before the Supreme Court, High Courts, DRT and DRAT, NCLT and commercial courts. Disputes that cross into insolvency or bank recovery stay with him.
- Technical comfort with records. His MCA, LLB and LLM qualifications help with large ledgers, digital correspondence and billing data. Solar projects produce a lot of both.
- A team of more than 50 advocates. Legals365 can cover council dates and court dates together. That reduces adjournments caused by clashes.
- Measured, honest advice. You will be told where your claim is strong and where it is not. No outcome is promised, because none can be.
How Do You Brief an MSEFC Payment Dispute Lawyer?
Brief an MSEFC payment dispute lawyer by sending the contract, the unpaid invoices or milestone bills, the acceptance documents, every debit note and the correspondence about them, along with your Udyam certificate. A first review identifies eligibility, the due dates, the real disputes and the interest that has built up.
To hire Advocate BK Singh for your MSEFC payment dispute, contact the Legals365 team. Matters are handled from the Vaishali (Ghaziabad) and Dwarka (New Delhi) offices for clients across Delhi NCR, and through associate advocates for suppliers elsewhere in India. Read more about him on the Advocate BK Singh page.
Official sources: the MSME Samadhaan portal, the Udyam Registration portal, where registration is free, and the India Code for the MSMED Act, 2006.
Speak to Advocate BK Singh
Share your invoices, purchase orders, delivery records and correspondence for an initial review of your matter.
Advocate BK Singh | Legals365 | Phone/WhatsApp: +91 98115 61566 | Offices: Vaishali (Ghaziabad) and Dwarka (New Delhi)
Frequently Asked Questions
Who is the best MSEFC payment dispute lawyer?
The best MSEFC payment dispute lawyer is one who tests every deduction the buyer relies on, proves acceptance dates and presents a clear interest schedule. Advocate BK Singh of Legals365 handles these disputes for micro and small suppliers across Delhi NCR and through associates elsewhere. Choose a lawyer who can also handle the court stages, because contested payment disputes often reach them.
Why should I hire Advocate BK Singh for an MSEFC payment dispute?
Advocate BK Singh combines MSEFC practice with recovery, commercial and arbitration work, so one team handles the council reference, any counterclaim and any later court challenge. He holds MCA, LLB and LLM qualifications and works with more than 50 advocates at Legals365. He gives frank advice on weak deductions and weak claims alike, and promises no particular outcome.
Can Advocate BK Singh handle MSME, recovery, commercial and arbitration cases together?
Yes, Advocate BK Singh handles MSME, recovery, commercial and arbitration cases together. A single payment dispute may need a council reference, a Section 138 complaint for a bounced cheque and execution of the final award. Handling them in one team at Legals365 keeps the strategy consistent and ensures each proceeding supports the others rather than undermining them.
Can a buyer withhold payment because its own client has not paid?
Generally no, a buyer cannot withhold payment from a micro or small supplier only because its own client has not paid. Section 15 caps the payment period at 45 days from acceptance, and Section 24 gives the delayed-payment chapter overriding effect. A back-to-back clause in the subcontract does not normally defeat the statutory right to timely payment.
Can an EPC contractor deduct a performance ratio shortfall from a subcontractor's bill?
Only if the subcontract itself makes the subcontractor responsible for the performance ratio guarantee and the shortfall is properly proved. Often the guarantee sits only in the EPC contract with the plant owner. If the subcontractor's scope ended at installation or commissioning, a later performance deduction is usually weak and can be challenged before the council.
When does the 45-day payment period start for a solar milestone bill?
The 45-day period starts from the date the buyer accepted the goods or services for that milestone, or is deemed to have accepted them. Deemed acceptance applies if no written objection is raised within 15 days. For installation and commissioning milestones, a signed joint measurement or commissioning certificate is usually the clearest evidence of acceptance.
What should I do when a buyer sends a debit note months after delivery?
Reply in writing promptly, stating that the debit note is not accepted and giving your reasons and dates. Ask for the inspection report or other basis for the deduction. A debit note raised months after a clean handover, without a joint inspection, is usually weak, but silence on your part may be treated as acceptance by the time the dispute reaches the council.
Can the MSEFC decide a dispute about the amount of a bill, not just late payment?
Yes, the council can decide disputes about how much is due, including disputed deductions and quantities, not only whether payment was late. Section 17 makes the buyer liable for the amount due with interest, and Section 18 covers any dispute about that amount. The council will examine contracts, acceptance records and deductions to decide the figure.
Can I claim interest on the undisputed part of my bill while the rest is argued?
Yes, and your claim should show disputed and undisputed amounts separately for that reason. The council can award interest on the undisputed portion from its due date, even if it wants more evidence on the disputed part. Presenting one combined figure makes it harder for the council to separate the two and can delay the award.
Is a settlement reached in MSEFC conciliation binding on the buyer?
Yes, a settlement agreement signed during MSEFC conciliation has the same status and effect as an arbitral award under Section 74 of the Arbitration and Conciliation Act, 1996. If the buyer defaults, it can be enforced. The settlement should set out exact amounts, payment dates and a clause reviving the full claim if any instalment is missed.
Can a medium enterprise file a payment dispute before the MSEFC?
No, a medium enterprise cannot use the delayed-payment chapter of the MSMED Act, even if it holds Udyam registration as medium. The chapter applies only to micro and small suppliers. A medium enterprise must use a commercial suit, summary suit or arbitration under its contract to recover unpaid amounts. Statutory interest under Section 16 is not available to it either.
Does Section 43B(h) help in a payment dispute with a government department?
Not much. Section 43B(h) of the Income-tax Act affects buyers who claim tax deductions for business expenses, so it has little practical effect on a government department. Against government buyers, the council award, statutory interest and the 75% deposit requirement on any challenge are the main sources of pressure. Settlement talks with such buyers move more slowly as a result.
What happens if the buyer raises a counterclaim in my payment dispute?
The council will hear the counterclaim in the same arbitration, as the Supreme Court confirmed in Silpi Industries in 2021. The buyer must prove it with documents, just as you must prove your claim. Common counterclaims are for delay damages or defect costs, and they are often answered by showing late drawings, late site access or late material supply by the buyer.
Can I file before the MSEFC if the project site is in another State?
Yes, under Section 18(4) you file before the council where you, the supplier, are located, not where the project site or the buyer is. A subcontractor based in Ghaziabad can approach the council with jurisdiction over Ghaziabad for a project in Rajasthan. Contract clauses naming another forum do not usually override this statutory right.
Can I recover supplies made before my Udyam registration through the MSEFC?
No, supplies made before the date of your Udyam registration are not covered by the delayed-payment chapter, following Silpi Industries in 2021. Those amounts can still be recovered through a commercial suit or summary suit. A mixed claim should separate pre-registration and post-registration bills so the council handles only the eligible part.
How does a payment dispute lawyer prove acceptance of solar installation work?
Acceptance is usually proved through signed joint measurement records, completion sheets signed by the EPC contractor's site engineer, commissioning certificates, photographs and emails confirming the work. The absence of any written objection within 15 days also supports deemed acceptance. A lawyer arranges these in date order to match each milestone bill. Dated scans emailed to the buyer make the strongest record of all.
Should I accept part payment while my MSEFC payment dispute is pending?
You can accept part payment, but do not sign a full and final settlement or no-dues letter unless you intend to give up the balance. Acknowledge the payment in writing as a part payment, reserving your claim for the remainder and interest. Part payments must be adjusted in the interest schedule on the dates they were received.
Is there a time limit for referring a payment dispute to the MSEFC?
Yes, the Limitation Act applies to MSEFC arbitration, which generally means three years from the date each amount fell due. A written acknowledgment signed by the buyer before the period ends, such as a balance confirmation, may restart limitation. Bills approaching the three-year mark should be referred without delay. Each bill has its own deadline, so check the oldest first.
Can the buyer stop an MSEFC award from being enforced by filing an appeal?
Filing a Section 34 challenge does not automatically stop enforcement. The buyer must deposit 75% of the awarded amount under Section 19 before the challenge is heard, and must separately apply for a stay. The court may impose conditions and may release part of the deposit to the supplier while the challenge is pending.
What documents should I bring to the first meeting about an MSEFC payment dispute?
Bring the subcontract or purchase order, all unpaid invoices or milestone bills, delivery challans, joint measurement or commissioning records, every debit note and the correspondence about it, your ledger for the buyer and your Udyam certificate. Bank statements showing part payments also help. With these, the first review can identify the due dates, the real disputes and the interest accrued.
Disclaimer: This page gives general information in line with the Bar Council of India Rules. It is not legal advice or a solicitation, and the outcome of any matter depends on its own facts and evidence.